I was recently working with a producer in New Mexico who was experiencing liquid slugs on a recently fracked well. His team was having to perform regular shut-ins to deal with them, and he asked if there was any way we could help.

Fluid Density and Liquid Slugs

A producer injects his fracked well with sand and chemicals in order to stimulate it. For the first few days, he can expect the well to bring a varying mixture of sand, chemicals, and water to the surface. After that the well starts cleaning up, and gradually they will see more and more oil. It typically takes 3-4 days before he’ll see an oil level in his knockout.

In an ideal scenario, what he wants is to complete the well and start flowing back and maintain a set flow. What he doesn’t want are peaks and valleys with liquid slugs or shut-ins. However, this can be a challenge when the density of your process fluid changes after stimulation.

The Challenge of Changing Fluid Density

Problem: Operational Downtime
Root Cause: Fluid density changing from everything they inject along with produced water

The chemistry of a well’s produced solution changes significantly when it transitions from everything injected to everything the ground gives up. So much so, in fact, that the float buoyancy in a separator and the weight it takes to make that interface is no longer viable. So, an operator is regularly forced to shut-in and re-weight the float.

The process for my New Mexico customer went like this: The construction crew would weight the float to an expected produced fluid density, and flowback would begin. Then fluid densities would change as the well produced, forcing the construction crew to shut-in and re-weight the float by shutting in and either adding or removing weight from the float internals.

This would be done by three guys, and the process would take approximately three hours from beginning of the shut-in process to final installation of the newly weighted float. From the company’s perspective, that’s three hours of pay for three operators, plus the revenue lost while production was paused. This could also be exacerbated if they wanted to do a check in the separator. This required a confined space point set up for the roustabout to examine.

DIY Attempts

I’ve seen a lot of of things used to weight a float rod on a liquid level control system, including rocks, sand, and random piping lying around. These were all employed to try to deal with a decrease fluid density while avoiding costly shut-ins.

After my visit with this producer in New Mexico, I met with our product team to see if we had anymore precise options we could offer. The solution was actually much easier than I anticipated.

Simple Solution: How to Weight Valve to Avoid Liquid Slugs

Proposal: Weight the float heavier than needed before start up, and install a longer lever arm with a weight.
Operating Principle: Counterbalancing the weight and adjusting on the lever arm as density changed would keep interface  Our product and engineering teams put their heads together, and quickly came up with a solution.

We already used a bar with small weights on our mechanical treater valves in order to maintain a specific volume in a liquid column. After some calculations, we determined that we could use this same solution on a trunnion assembly and dump valve to provide the required functionality for this application.

Our engineers created a custom calculator for it and a tool to give a point of reference for the weight location on the bar. Now, rather than a trial-and-error process with a bucket of rocks, we had a standard, simple solution in place and a precise calculation to deal with this problem.

The customer ordered an assortment of our 7, 9, and 11 pound weights to use as needed on their separators. If you’d like to discuss this solution for your operation, contact your local Kimray Representative!